International Energy Technik

Uganda Projects

Construction of 33KV Evacuation infrastructure at ACWA II

Design, Supply , Installation, Testing & Commissioning of 33KV&11KV GIS Switchgear, 15/20MVA,33/11.55KV Transformer and SCADA system along with associated CIVIL Works

Completed Year: 2019

Construction of BOMBO 33/11kV Sub Station asset Replacement Project

Design, Supply , Installation, Testing & Commissioning of 33KV GIS Switchgear, 7.5/10MVA,33/11KV Transformer and SCADA system along with associated CIVIL Works

Completed Year : 2020

CROWN BEVERAGES LIMITED

Design, Supply, Installation, Testing & Commissioning of 800KVA UPS

Completed Year: 2023

Upgradation of KAWANDA 132KV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 132KV Substation, 40MVA,132/33KV Power Transformer,132KV Outdoor Bay and SCADA system along with associated Civil Works

Completed Year : 2019

Upgradation of KISUBI 33KV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 15/20MVA and Relay Upgradation along with associated Civil Works

Completed Year : 2020

Construction of NAKAWA 33/11kV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 33/11KV Compact Substation, 15/20MVA,33/11KV Transformer and SCADA system along with associated CIVIL Works

Completed Year : 2020

Namanve RING Project

Design, Supply , Installation, Testing & Commissioning of RMUs in Different Locations which covers 25kms including 33kv underground power cables along with associated Civil Woks

Completed Year : 2020

Upgradation of NKANDA 132KV SUBSTATION

Design, Supply, Installation, Testing & Commissioning of 132KV Substation, 80MVA,132/33KV Power Transformer,33kv switchgear, 132KV Outdoor Bay, and SCADA system along with associated Civil Works

Completed Year: On-going project

Ntake Bakery & Refinery Oil Electrical & Instrumentation Project

Design, Supply, Installation, Testing & Commissioning of 33/440V 1.6MVA Transformer 33KV Switchgears, LV Panels for Powerhouse, Chemical Stores, WTP, Boilers, Fire Fighting, Soap Plant, Refinery Section, Packing Section, Workshop, Weighbridge with 120kms of Cable lying with Cable trays

Completed Year: 2024

UBL 11KV POWER UPGRADE PROJECT

Design, Supply, Installation, Testing & Commissioning of 11KV Switchgear Compact Substation, 2.5MVA Transformer, 1250kVA DG Set with sync Panels and SCADA System.

Completed Year: 2023

Water & Solar

Installed numerous watts of solar panels across Uganda, including solar power backup systems and water pumping systems.

Construction of 33KV Evacuation infrastructure at ACWA II

Design, Supply , Installation, Testing & Commissioning of 33KV&11KV GIS Switchgear, 15/20MVA,33/11.55KV Transformer and SCADA system along with associated CIVIL Works

Completed Year: 2019

Construction of BOMBO 33/11kV Sub Station asset Replacement Project

Design, Supply , Installation, Testing & Commissioning of 33KV GIS Switchgear, 7.5/10MVA,33/11KV Transformer and SCADA system along with associated CIVIL Works

Completed Year : 2020

CROWN BEVERAGES LIMITED

Design, Supply, Installation, Testing & Commissioning of 800KVA UPS

Completed Year: 2023

Upgradation of KAWANDA 132KV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 132KV Substation, 40MVA,132/33KV Power Transformer,132KV Outdoor Bay and SCADA system along with associated Civil Works

Completed Year : 2019

Upgradation of KISUBI 33KV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 15/20MVA and Relay Upgradation along with associated Civil Works

Completed Year : 2020

Construction of NAKAWA 33/11kV SUBSTATION

Design, Supply , Installation, Testing & Commissioning of 33/11KV Compact Substation, 15/20MVA,33/11KV Transformer and SCADA system along with associated CIVIL Works

Completed Year : 2020

Namanve RING Project

Design, Supply , Installation, Testing & Commissioning of RMUs in Different Locations which covers 25kms including 33kv underground power cables along with associated Civil Woks

Completed Year : 2020

Upgradation of NKANDA 132KV SUBSTATION

Design, Supply, Installation, Testing & Commissioning of 132KV Substation, 80MVA,132/33KV Power Transformer,33kv switchgear, 132KV Outdoor Bay, and SCADA system along with associated Civil Works

Completed Year: On-going project

Ntake Bakery & Refinery Oil Electrical & Instrumentation Project

Design, Supply, Installation, Testing & Commissioning of 33/440V 1.6MVA Transformer 33KV Switchgears, LV Panels for Powerhouse, Chemical Stores, WTP, Boilers, Fire Fighting, Soap Plant, Refinery Section, Packing Section, Workshop, Weighbridge with 120kms of Cable lying with Cable trays

Completed Year: 2024

UBL 11KV POWER UPGRADE PROJECT

Design, Supply, Installation, Testing & Commissioning of 11KV Switchgear Compact Substation, 2.5MVA Transformer, 1250kVA DG Set with sync Panels and SCADA System.

Completed Year: 2023

Water & Solar

Installed numerous watts of solar panels across Uganda, including solar power backup systems and water pumping systems.